allinmodular.com / Guides / Module transport
Guide · Logistics

Shipping data center modules: sizes, road limits and logistics

The road decides how big a module can be. This guide gives the container and EU road limits, explains when a load becomes oversize, counts the truckloads for a 20 MW project and covers cranes, sequencing and the joints on site.

Updated October 20267 min readBy Ziya DemirData center project directorFounder of allindatacenter.com

In short

  • EU standard road loads: up to 2.55 m wide, 4.0 m high including the trailer, 16.5 m articulated (Directive 96/53/EC).
  • Wider or taller loads need permits; beyond about 3.5 m wide or 4.5 m high expect escorts and route surveys.
  • A 20 MW project with 1 MW pods needs roughly 110–115 truckloads of modules.
  • Splitting a module is often cheaper than moving an abnormal load.
Limits

Container and road limits

EnvelopeLengthWidthHeightNotes
20 ft container (inside)5.90 m2.35 m2.39 mSmall edge modules, spares
40 ft high cube (inside)12.03 m2.35 m2.69 mContainerised UPS, batteries, edge
EU standard road vehicle16.5 m artic.2.55 m4.0 m totalDirective 96/53/EC; height includes the trailer
Oversize loadlongerup to ~3.5 mup to ~4.5 mNational permits
Abnormal loadroute-specificbeyond ~3.5 mbeyond ~4.5 mEscorts, route survey, night moves

Oversize thresholds are indicative and set nationally. Check a module envelope in the logistics section.

Height

The height trap

The 4.0 m limit includes the trailer deck. A module 3.0 m tall on a 0.9 m deck is 3.9 m overall and still a standard load; the same module on a 1.2 m deck is oversize. Low-loaders with decks around 0.5–0.9 m buy back that margin. Width and height usually decide the module; length is easier to manage.

Count

Counting truckloads for a 20 MW project

ItemRuleCount
White-space pods of 1 MW20 MW ÷ 1 MW20 pods
Pod shipping sections4 sections per MW × 2080 loads
Power skids of 2.5 MVA, N+120 MW × PUE 1.3 ÷ (2.5 MVA × 0.95) = 11, + 112 loads
Cooling modules of 1,000 kW20,000 ÷ 1,000 + 121 loads
Total113 loads

With 2N power the skids double to 22 and the total rises to 123. Sections per MW depend on the product; ask the supplier.

Count modules and loads for your projectThe planner adjusts pod size, skid rating, cooling module size and topology.
Open the planner →
Site

Cranes, laydown and sequencing

  • Cranes: heavy power skids and transformers can weigh 20–40 t or more; crane size depends on weight and reach, so plan crane positions and ground bearing early.
  • Laydown: keep space for a few days of deliveries; modules should go straight from truck to foundation where possible.
  • Sequence: power first, then cooling, then white space, matching the order of commissioning.
  • Weather: plan lifting windows; wind limits stop crane work.
  • Protection: modules arrive sealed; keep them dry and closed until connected.
Connections

Joints on site

Good modular design keeps site connections few and simple: busway or cable joints, flanged pipework and pre-terminated network links. Joints are sealed against weather and fire, torque-checked and documented, then proven with the rest of the system in the site integrated test.

Questions

Questions about module transport

What is the largest module that can go by road?

Without permits, 2.55 m wide and 4.0 m high including the trailer in the EU. With permits and escorts much larger loads move, but cost and route limits grow fast.

Can modules be shipped by sea?

Yes. Container-sized units go as standard freight; larger skids travel as breakbulk or on flat racks, then by road from the port.

How heavy is a power skid?

It depends on the rating and whether the transformer is on the skid. Ask the supplier early; weight sets the crane and the trailer.

Should I split a large module?

Often yes. Two standard loads with one site joint are usually cheaper and faster than one abnormal load with escorts and a route survey.

Sources

Sources

  • Directive 96/53/EC (EU maximum dimensions); typical ISO container inside dimensions.
  • Load counts follow the module planner on this site; sections per MW are an assumption to edit.
  • Oversize thresholds are indicative and set nationally.
Next

Keep reading